Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

¿Cuál alimento es parte de una típica comida de Día de Acción de Gracias en Puerto Rico?
Brad has 42 stamps to arrange on an album page Part A: Which of the following are possible arrays Brad can make with the stamps? Choose all that apply A. 2 × 2
someone please help
A random change in the sequence of DNA is called a
In January 2011 the rate of VAT increased from 17.5% to 20% work out the difference in price of a car worth £15000 +VAT due to increase in VAT Please can u help
20 feet+ 23 feet+ 19 feet +8 feet+ 13 feet +5 feet +32 feet +41 feet +45 feet
2143.57333 whole number
What is a physical change? new substance no new substance both substances neither substance
What is the area of a square with a side length of square root of 13
x + 10 = 2x + 8 Please solve and explain, please. Whoever has the best explanation will get the brainlest answer.